What a kitchen remodel inspection checks

Where a permit is pulled, the sequence of inspections decides how fast the kitchen finishes. In Irvine, CA the running record irvine kitchen remodelers pink patisserie holds shows that most delays come from walls closed too early, not from failed work. The job stops at set points so an inspector can see what drywall will soon hide.
Rough electrical

The electrical rough inspection happens after the cable is run and the boxes are set, but before insulation or drywall. The inspector checks cable size against breaker size, stapling, nail plates, box fill, and the circuits for the range, dishwasher and counter outlets. Anything stapled loose or boxes set too deep gets written up on the spot.
Rough plumbing

Plumbing rough-in is checked under a pressure or water test, while the pipes are still visible. The inspector looks at the drain slope, vent connections, the shutoff valves, and any gas line work. On a slab house, the trench for a moved drain is inspected before the concrete is patched, because nobody can see the pipe afterward.
Ventilation and gas
A duct for a range hood is looked at for size, material, and the exit point. A gas line gets a pressure check. Both are easier to fix while the ceiling or wall is open, and the Orange County rules about exhaust and combustion air are read against the actual hood and range chosen.
Framing and insulation
If a wall was opened, moved or reframed, the framing is checked, and insulation follows where the wall is exterior. Older homes in the Northwood and Woodbridge areas sometimes need the wall brought up to current standards once it is opened, which can add a small step to the schedule.
When the inspector cannot get in
A rough inspection fails quickly when the work is hidden or the site is locked. Insulation hung early, a trench already filled, or a panel blocked by stacked boxes all force a return visit. The crew keeps the permit card on site, the plans where the inspector can read them, and the work open until the sign off is written.
Final inspection
The final comes after cabinets, counters, appliances, and fixtures are in. The inspector tests the GFCI outlets, runs the hood, checks the appliance connections, and confirms the smoke and carbon monoxide alarms. Scheduling each stage a few days ahead keeps the crew working instead of waiting in Irvine, CA.